Handwritten one-page note: Gantt Charts in One Page
Tap the note to see it full size

Productivity One-page note

Gantt Charts in One Page

Every project plan you've ever seen in a business class, in one page: bars, dependencies and the critical path. Save this page.

Good to know

Terms follow the APM (Association for Project Management) glossary.

What's on the page

The note as text, so you can read it, copy it or use a screen reader.

What it is

  • Tasks down the side
  • Time along the top
  • One bar per task
  • Bar length = how long it takes

Key words

  • Dependency: B waits for A
  • Critical path: longest chain, start to finish
  • Float: spare time a task has
  • Milestone: a key moment (◆)

Worked example: a bake sale

  • A Book hall: 2 days
  • B Posters: 3 days (after A)
  • C Bake: 2 days (after A)
  • D Sale day: 1 day (after B and C)

Read the answer

  • A→B→D = 6 days (critical path)
  • A→C→D = 5 days
  • C has 1 day of float
  • Delay B, and the sale moves

Do / Don't

  • Draw arrows for dependencies
  • Update it as things change
  • Too many tasks to read
  • Forgetting waiting time

Sources

  1. APM (Association for Project Management): What is a Gantt chart?
  2. APM: Glossary of project management terms
  3. Wikipedia: Gantt chart

How we checked this

Every fact on this note comes from the 3 sources listed here, checked against official or peer-reviewed sources where possible. AI tools help with drafting; a person checks every fact against the sources. How we research

Spotted a mistake? Tell us and we'll fix it and log it on the corrections page.

More from Productivity

All Productivity notes →