Gantt Charts in One Page
Every project plan you've ever seen in a business class, in one page: bars, dependencies and the critical path. Save this page.
Good to know
Terms follow the APM (Association for Project Management) glossary.
What's on the page
The note as text, so you can read it, copy it or use a screen reader.
What it is
- Tasks down the side
- Time along the top
- One bar per task
- Bar length = how long it takes
Key words
- Dependency: B waits for A
- Critical path: longest chain, start to finish
- Float: spare time a task has
- Milestone: a key moment (◆)
Worked example: a bake sale
- A Book hall: 2 days
- B Posters: 3 days (after A)
- C Bake: 2 days (after A)
- D Sale day: 1 day (after B and C)
Read the answer
- A→B→D = 6 days (critical path)
- A→C→D = 5 days
- C has 1 day of float
- Delay B, and the sale moves
Do / Don't
- Draw arrows for dependencies
- Update it as things change
- Too many tasks to read
- Forgetting waiting time